Carrington Construction March Update
March 6, 202327/4/23
We are proud to report that the construction of Carrington is well underway! March has been a busy month for the team at Carrington, with works across the stages under construction progressing well.
Stage 3
Anticipated Settlement Date: mid 2023
Stage 4
Civil works for Stage 4 have been completed, with the Statement of Compliance process underway.
Anticipated Settlement Date: May 2023
Stage 5
Footpath works continuing into May 2023.
Anticipated Settlement Date: June 2023
For more information, please get in touch with our friendly sales team at carrington@oliverhume.com.au or call 03 9684 8114.